    • #74216
      celine.muthukumaran
      Participant

      Hi All, and Fiona,

      In relation to aircon during building work, my experience @ MRHP was risk assessed – with ward , location, patient case load to those exposed bay’s /rooms and we chose aircon for temperature regulation with closure/seal the windows during the initial excavation phase. The aircon had some level of noise pollution but had the vent pipe fixed/well sealed to the windows for air exchange

      Hepa-filter was considered pending on the high risk patient cohort/frequency and duration of potential dust exposure

      I am not sure if SHIVA air conditioning limited company are doing combined aircon/hepa filters !

      Hope this helps

      Thankyou

      Celine Muthukumaran